New Builds New Build 037

Week 13

Click on any of the images below to view in more detail.

The current state inside the accommodation section 

Studs have been welded on to secure the insulation in the accommodation section 

The current state of the engine room 

the deckhouse corridor now has the sides fitted 

Working on the for'ard end 

Progress on plating the starb'd side 

Progress on plating the port side 

Construction of the gantry has started 

The transom is being built 

Two auxiliary engines have arrived