New Builds New Build 037

Week 14

Click on any of the images below to view in more detail.

Early in the week the accommodation area had been painted out 

Later work was started on flooring out the accommodation area 

Bringing timber aboard to floor out the accommodation area 

An access opening has been cut into the engine room side 

Plating continues - starb'd bow 

Plating continues - starb'd side 

Plating continues - port bow 

Plating continues - port bow from the inside 

Early in the week a start was made on the sides to the lower aft deck 

Later plates are being added to the sides 

Fitting plates to the sides on the aft deck 

The stern tube waiting to be fitted 

Insides of some tanks have to be painted before the outer plates are attached