New Builds New Build 037

Week 22

Click on any of the images below to view in more detail.

The rudder post waiting to be fitted into its housing 

Grilles for cooling seawater have been cut through the hull 

Anther cooling water grille 

Insulation has been fitted in the deckhouse and lining has begun 

D-section reinforcement strips are being fitted around the hull 

Welding on the D-section reinforcement 

Lockers are being built in the accommodation area 

Two auxiliary engines have ben lifted into the engine room 

The main propulsion unit and gearbox are also now in the engine room 

Rapid progress on building the nozzle this week 

Fitting another part to the nozzle