New Builds New Build 037

Week 27

Click on any of the images below to view in more detail.

The mount for the landing crane has been fitted to the deck 

The duct for the exhausts has been built up the starboard side of the wheelhouse 

Coamings have been built around the main hatches 

An escape hatch and ventilation duct have been fitted behind the wheelhouse 

The main engine has now been seated and connected to the gearbox 

A general view of the engine room 

Lining of the fishroom has begun 

Sea cocks have been fitted through the engine room plating 

The starboard side of the shelter deck has now been plated 

Progress on the skipper's cabin 

Floor units are being fitted into the galley (Monday) 

Wall units are being fitted into the galley (Friday) 

The back of the wheelhouse - window frames are now fitted 

Windows frames have also been fitted in the front of the wheelhouse 

Preparing to fit the prop shaft 

The prop shaft going into the stern tube