New Builds NEW BUILD 038

Week 28

Click on any of the images below to view in more detail.

Bollards are being fitted this week 

The fairleads are also being fitted 

A completed fairlead fitting into the hand rails 

The fish room ceiling has been spayed with polyurethane foam insulation 

Later the insulation on the fish room ceiling has been covered with plywood sheeting 

Panelling continues in the wheelhouse 

Looking up to the wheelhouse ceiling 

Just starting to build the display console along the front of the wheelhouse 

Hand rails have been fitted all around the upper deck 

Hand rails around the bow 

Fitting of pipework within the engine room continues