New Builds New Build 037

Week 29

Click on any of the images below to view in more detail.

All the exhausts are now in place and the top of the duct has been closed 

Watertight doors are being fitted at the moment - here in the shelterdeck 

Here in the deckhouse ... 

... and here on the aft main deck near the winches 

The fishroom ceiling has been sprayed with polyurethane insulation  

Work has also started on the plywood lining 

Most of the ceiling has been lined by Thursday 

On Monday building of the deck handrails had started 

By Thursday the rails are all but complete 

Construction of the wheelhouse floor has started 

Welding continues in the wheelhouse