New Builds New Build 037

Week 35

Click on any of the images below to view in more detail.

The temporary floor has been removed from the fishroom and insulating has started 

The connections to the side thruster can now bee seen on the fishroom for'ard floor 

The plastic 'doubler' is being prepared to protect the sides from damage by the trawl gear 

Cabling continues in the galley 

Painting has just started in the mess 

A stainless steel sink unit for the galley has arrived 

A guard for the tow cables has been built for'ard of the wheelhouse 

Work continues on the nozzle, which has been turned over