New Builds NEW BUILD 042

Week 36

Click on any of the images below to view in more detail.

Fitting out of the accommodation area continues 

Progress so far in accommodation 

More fitting still to do in accommodation 

The bunks in accommodation by the end of the week 

Fitting a cable try in the engine room 

Fitting pipework for one of the engine's cooling system 

More parts are being fitted for one of the exhaust systems 

The fish room is about ready to be lined 

Electrics for the rudder controls are being fitted 

The wheelhouse floor is being laid 

The wheelhouse roof has been insulated 

The wheelhouse walls have also been insulated